9.2 Long-Term Operating and Capital Improvements
Capital & Infrastructure Implementation of capital improvements and periods: » New and replacement vehicles (FY 2030) » Key West Intermodal Center Improvements (2030) » Bus Stop Improvements (2030) » ADA Assessment and Transition Plan (2030) Table 9-5 provides a prioritized and chronological summary list of the Long-Term Plan timeframe. Table 9-5: Long-Term Plan Summary Timeframe (Years 5-10)
Implementation Year
1st Year Annual Operating Cost
Total Capital Cost
Need
Planned Improvement
30 31 32 33 34
Expand Existing Service Workforce Express: Increase Frequency
$3,250,922
$1,400,000
New & Expanded Service
R
New Service: SouthConnector New & Replacement Vehicles Key West Intermodal Center
$1,261,447
$350,000 $2,350,000 $32,000,000
R
R R R R R
R R R
Bus Stop Infrastructure & Accessibility Program Development & Implementation of Marketing Program Completion of Bus Stop and Transit Facility ADA Transition Plan
$250,000
R R R R R
Capital & Infrastructure
$125,000
R R R R R
$200,000
R